They still haven't paid. What can I claim?

Work out what you can claim, then get the letter that claims it. Free, and nothing you type leaves your browser.

Who owes you

Who owes you
How is that business set up?
Were they buying for their business?
Do they meet the public-authority definition for the nation you selected?

The invoice

The total as you billed it, VAT and all.

Payment terms
days

Part payments

Interest

Rate in your contract
%

Dates

Contract

Could another Act or legal rule already give you interest on this debt?

Conduct

Could anything you did have caused the late payment or justify reducing the interest?

Dispute

Procedure

Nation

Where you would bring a claim

Your details

Your trading status

Their details

The job

How was the job agreed?

Payment

Deadline

Days to reply
days

Tone

Tone

Example figures
Calculated

Total now due

£2,455.95

Your letter

What you have already sent
Stage

https://industryoversight.co.uk/tools/late-payment-interest-calculator/

If the calculator will not run

The calculator needs JavaScript. The two tables below are the same dated constants it works from, and the worked example is the one it shows on opening.

Worked example: a £2,340.00 invoice, 30-day terms, 61 days late, interest to 24 August 2026

RowAmount
Invoice total£2,340.00
Balance outstanding£2,340.00
Statutory interest, 61 days at 11.75% a year£45.95
Fixed compensation£70.00
Total now due£2,455.95

Statutory rate by reference date

Reference dateBank Rate in forceStatutory rateApplies where interest starts to run
30 June 20235.00%13.00%1 July to 31 December 2023
31 December 20235.25%13.25%1 January to 30 June 2024
30 June 20245.25%13.25%1 July to 31 December 2024
31 December 20244.75%12.75%1 January to 30 June 2025
30 June 20254.25%12.25%1 July to 31 December 2025
31 December 20253.75%11.75%1 January to 30 June 2026
30 June 20263.75%11.75%1 July to 31 December 2026

Fixed compensation bands

Size of the debtFixed sumHow the Act puts it
Under £1,000£40.00A debt under 1,000 earns the 40.00 sum.
£1,000 to £9,999.99£70.00A debt of 1,000 or more and under 10,000 earns the 70.00 sum.
£10,000 or more£100.00A debt of 10,000 or more earns the 100.00 sum.

We hold rates for interest starting between 1 July 2023 and 31 December 2026. A debt starting outside that window gets no figure at all rather than a guess.

Where the number comes from

Nothing here is generated. Three rules produce every figure on the card, always in the same order, and every one of them comes out of a document you can open for yourself.

Interest starts the day after the debt became late, at the rate set by the half-year reference date before it, and it keeps running while you read this.

When the invoice actually became late

Agree a payment date and that is the date. Agree nothing, expressly or by implication, and the law normally gives your customer 30 days, counted from the later of two events: the day you finished the work, or the day they had notice of what they owed. Interest starts the day after.

Agree a long date and there are caps. A public authority is held to the end of the 30-day period. Another business is held to the end of the 60-day period, unless the day you agreed is not grossly unfair to you, which is a judgement about your bargain, not a sum. Some facts we hold rather than guess at, among them an acceptance or verification procedure, an advance payment, and hire with periodic payments. Tick one of those and you still get the debt on screen, without a formal claim built on a rule we haven't implemented.

The statutory interest rate, and why it does not move

On a commercial debt it is 8 per cent over the Bank of England base rate. The part that catches people out is which base rate. Article 4 of the 2002 rate order fixes it once, by reference to the 30 June or the 31 December immediately before your interest starts running, and there it stays. If the Bank moves next month, your figure doesn't move with it. Plenty of calculators re-split the sum at every base-rate change, which hands the debtor's accountant something to pull apart.

We ship the reference rates as dated rows, and they run out on 31 December 2026. A debt whose interest starts outside that window gets no interest figure at all, only the reference date we would need to work it out. A rate we can't vouch for is worse than no rate, because it goes into a demand for money under your name.

The fixed compensation band

On top of the interest, a qualifying late commercial debt earns a flat sum for the trouble of chasing it, and you don't have to prove you spent anything to get it. The cut-offs are strict, which is the bit worth reading twice. Strictly less than one thousand pounds takes the forty-pound sum, and a debt of exactly one thousand pounds does not. One thousand or more, and strictly under ten thousand, takes seventy. Ten thousand or more takes a hundred, and exactly ten thousand counts as ten thousand or more.

One penny of debt therefore moves the compensation by £30.00, which is why we spell the boundaries out in words. Where chasing the debt has cost you more than the fixed sum, the Act lets you claim the difference, and the letter says what that sum is for.

How we round, and why we round down

We work the interest out exactly across the whole period and floor it to the penny once, right at the end. Two things follow. Your letter never claims more than the unrounded result under that method. And the daily figure on the card, multiplied by the days, lands a little under the interest to date: on the worked example, £0.75 a day across 61 days is £45.75, against £45.95 of interest.

That 20p gap is rounding we deliberately don't compound. Round first and multiply afterwards and the error grows with every day that passes. The Act does not prescribe a rounding rule, so this one is our choice, and the working says so rather than dressing it up as the law.

Part payments run on the same arithmetic. Interest accrues on what was actually outstanding on each day and steps down from the day each payment arrived, which visibly flattens the slope. What the sources we opened don't settle is which figure then sets the compensation band: the invoice as billed, or the balance left afterwards. So you get the interest working, and we hold the fixed sum and the total until you have taken advice, rather than picking one and hoping.

Two customers, two completely different letters

This is the part a generic template gets wrong, and it's the part that can land you in trouble.

The first question on the page decides what the letter is allowed to say. The letter builder never sees a clause the rules forbid, so it cannot assemble one.

A buyer acting in the course of a business

The Late Payment of Commercial Debts (Interest) Act 1998 applies where the buyer and the seller are each acting in the course of a business. A limited company, a partnership, a letting agent, a main contractor, a council: all in. On those debts you can claim the debt itself, statutory interest and the fixed sum, subject to the Act's own exclusions and to any competing remedy sitting in your contract.

A private homeowner having a bathroom done

Not in, and no amount of firm wording changes it. Tell a homeowner in writing that they owe you statutory interest and a fixed sum under a 1998 Act, and you have made a false statement about their legal position inside a demand for money. Since April 2025 that risks being a misleading commercial practice where it is likely to change the average consumer's transactional decision, and an unlawful action threat is one of the factors that decide whether a practice is aggressive. We'd rather not be explaining it.

So we don't build that letter. Pick A private homeowner and the Act disappears from the card and from all three drafts. What you can still claim is the debt. An agreed term may support interest, but we hold the figure and the demand until the whole term has been read, and we ask for the written wording as evidence, which is our own scope rather than a rule that every term has to be in writing. A term that piles on a disproportionately high sum can be unfair and not binding under the Consumer Rights Act 2015, so a punchy rate isn't the weapon it looks like.

The sole trader who is in both camps at once

A sole trader buying for his business sits on both sides at the same time. The Act applies to him, so the interest and the fixed sum are yours. He is also an individual, which brings in the Pre-Action Protocol for Debt Claims: thirty days rather than fourteen, and a named list of things to put in the envelope. Get that one wrong and a perfectly good claim starts on the back foot. Both halves of the market miss it, which is why the first question here is who owes you, not how much.

What a letter before action has to contain

A letter before action isn't a stern email. Where the Pre-Action Protocol for Debt Claims applies it is a document with a contents list, and the court will look at whether you followed it.

The protocol wants the amount, and whether interest and charges are still running. It wants to know how the job was agreed, and if it was agreed on the phone, who said what, and when and where. It wants how you can be paid, how to discuss payment options, and the address the reply goes to. Then it wants four things in the envelope.

Who owes you Which route Time to reply What goes in the envelope
A sole trader or a private individual, in England or Wales Pre-Action Protocol for Debt Claims, where no other protocol covers the debt 30 days from the date at the top of the letter Statement of account, Information Sheet, Reply Form, Financial Statement
A company, an LLP or a public authority, in England or Wales Practice Direction on Pre-Action Conduct and Protocols, where no other protocol covers the debt 14 days is the yardstick in a straightforward case A copy of the invoice and the interest working
An ordinary partnership Unresolved on the sources we opened, so we hold the final letter No default we can source A copy of the invoice and the interest working
Anyone, in Scotland or Northern Ireland Neither of the two above: both belong to England-and-Wales procedure No default we can source A copy of the invoice and the interest working

Put these in the envelope

  • An up-to-date statement of account for this debt.
  • The Information Sheet at Annex 1 to the protocol.
  • The Reply Form, from the same annex.
  • The Financial Statement form at Annex 2.

We print the first one for you. The other three come from the protocol itself, so download them, print them, and put them in with your letter.

After you post it

  • 1Date it near the top of the first page, and post it that day or the next.
  • 2Wait 30 days from that date before you issue anything.
  • 3If the Reply Form comes back, do not issue less than 30 days after you received it, or 30 days after you handed over any documents they asked for, whichever falls later.
  • 4Answer a request for a document or for information within 30 days.
  • 5If you have both had your say and still cannot agree, give at least 14 days' notice before you issue.

Where the debtor is a company, an LLP or a public authority, a lighter regime applies instead: the Practice Direction on Pre-Action Conduct and Protocols. It wants concise details of the claim, a summary of the facts, what you want from them, and how the amount is worked out. It treats fourteen days as a reasonable time to reply in a straightforward case. A construction or engineering dispute has its own route, so tick that box and we hold the generic final letter and point you at the Construction and Engineering protocol instead.

One thing worth knowing before you post anything. Both of those live in the Civil Procedure Rules, and those rules run in England and Wales. The 1998 Act reaches qualifying debts across the whole United Kingdom, but Scotland uses a different public-authority definition, and court procedure differs in Scotland and in Northern Ireland. We haven't sourced a pre-action route for either, so we hold the final-stage letter there and say so on the card, rather than handing you an English deadline to put above a Scottish address.

Late payment interest questions, answered

How much interest can I charge on an unpaid invoice?

If your customer is another business, 8 per cent a year over the Bank of England base rate, which puts it at 11.75 per cent at the moment. You do not need a late-interest clause of your own where the statutory term applies, though a competing contractual remedy or another statutory gate can change that. If your customer is a private homeowner, the answer is nothing at all unless your written terms say otherwise.

What is statutory interest?

Interest that the Late Payment of Commercial Debts (Interest) Act 1998 adds to a qualifying late business-to-business debt, where no exclusion or substantial contractual remedy displaces it. It is simple interest rather than compound, and it starts running the day after payment was due. A fixed compensation payment comes with it.

Can I charge a homeowner interest for paying late?

Only where you agreed a term, and even then the whole term needs checking before an amount is calculated or demanded. We record the written wording for that review rather than working a figure out from the rate on its own. The commercial Act does not reach consumers. A term that charges a disproportionately high sum can be unfair and not binding under the Consumer Rights Act 2015, so a punchy rate is not the win it looks like.

Do I need a solicitor to send a letter before action?

No. You can send it yourself, in your own name. What matters is that the letter says the right things and gives the right amount of time, and that is the part we do for you. If the job is disputed, or your contract has an interest term in it, that is the point to take advice rather than press on.

Can I send a letter before action by email?

Where the Debt Claims Protocol applies, which is normally a business chasing an individual, sole traders included, and no other protocol covers the debt: post it, and you may email it as well. If the debtor has explicitly asked you not to use post and given you other contact details, use those instead. For a company debtor there is no posting rule. Keep proof you sent it either way.

How long do I have to give them after a letter before action?

Thirty days from the date at the top of the letter if the debt protocol applies. Fourteen days is the yardstick for a straightforward claim against a company under the Practice Direction. If they reply, wait at least 30 days from receiving the Reply Form, or 30 days from providing any documents they asked for, whichever is later. If you still cannot agree, give at least 14 days notice before you issue.

Is a letter before action a legal requirement?

The court expects you to have followed the pre-action route that applies to your debt, and material non-compliance can affect case management, costs or interest. So the response period is part of the claim rather than a drafting preference. Shortening it to make a point is the edit most likely to cost you money later.

Can I claim the fixed compensation on every late invoice?

We handle one payment due under one invoice, and on that scope the fixed sum attaches once statutory interest starts running on that qualifying debt. The statute frames it per qualifying debt and GOV.UK puts it as once for each late payment. Forty pounds under a thousand, seventy from a thousand to just under ten thousand, and a hundred at ten thousand and above. Three qualifying late payments can mean three fixed sums.

How long can I chase an unpaid invoice?

In England and Wales, section 5 of the Limitation Act 1980 usually gives you six years from the day the cause of action accrued on a simple contract. Other facts can move that, so if an invoice is getting anywhere near six years old, take advice rather than a view.

Late payment interest calculator for UK trades

A qualifying late commercial debt in the UK may carry statutory interest at 8 percentage points over the applicable Bank of England reference rate, and a fixed sum of 40, 70 or 100 pounds, subject to the Act's exclusions and adjustments. Both come out of the Late Payment of Commercial Debts (Interest) Act 1998. Both may apply without an express late-interest clause, subject to those same exclusions, the contractual-remedy rules and the Act's adjustments. And both are easy to miss entirely.

We work the figure out for one qualifying payment, to the penny, and then write the letter that claims it: a friendly reminder, a firm second notice, or a full letter before action carrying the response period and the enclosures the applicable pre-action regime requires. It's free and there's no sign-up. Names, addresses, figures, dates and free text stay in your browser. The optional tone step sends one task label and five fixed choices, and nothing else.

Get paid on time more often

The cheapest version of this problem is not being better at chasing. It's picking customers who pay.

A listing puts your credentials, your pricing and your payment terms in one place before a customer ever picks up the phone. We list trades free: no referral fee, and the customer pays you direct.